Construction on a Google data center in Botetourt County must stop for now after a judge ruled Monday that the Board of Supervisors violated Virginia's open-meeting law when it approved an agreement tied to the project last year.
At Tuesday's board meeting, Chair Dr. Mac Scothorn said the county is weighing its legal options and that some things remain unknown. He said construction will be minimal for the rest of the year, limited to minor stabilization work so the site stays in compliance. Google said in a statement that it is evaluating the ruling and remains committed to working transparently with the county and community in full compliance with legal and regulatory requirements.
The board also pulled agenda items on starting work on a museum and funding renovations to the Buchanan library, because both are expected to rely on money the county is slated to receive from Google for the data center.
STARNEWS.PLUS
Original Facebook source: Open post
Source note: Star News TV · Nov 24, 2026 10:10 PM.
Community
Discussion
No comments yet. Be the first to respond to this report.